Tairāwhiti road recovery takes out Hawke’s Bay East Coast civil construction awards

A challenging road repair near Gisborne, a steel arch bridge reconnecting Wairoa communities and a flood wall protecting Pōrangahau were among the outstanding projects and people celebrated at the Hawke’s Bay and East Coast civil construction awards on Friday night.

A crowd of more than 200 people gathered to celebrate the region’s top infrastructure at Toitoi Hawke’s Bay Arts & Events Centre in Hastings for the Civil Contractors New Zealand Hawke’s Bay East Coast 32nd Annual Awards.

Exemplary recovery works on Tiniroto Road (pictured, below), southwest of Gisborne, earned a consortium led by Currie Construction the night’s Supreme Award, as well as the award for projects with a value between $1.5 million and $3 million. The consortium, made up of Currie Construction, QRS, Lattey Group and H. Blackbee Contractors, with LDE Ltd as consultant, restored and strengthened key sections of the vital Tairāwhiti transport route affected by slips, erosion and slope instability caused by severe weather events.

The judges noted the constrained road corridor and challenging ground conditions posed by the project, as well as Currie Construction’s completion of more than 14,000 work hours without a recordable injury.

“Through effective collaboration and value engineering, the project delivered a resilient long-term solution while reducing overall costs for Gisborne District Council.”

Replacement of Te Rēinga Bridge on Ruakituri Road won the award for projects valued over $10 million for Wairoa-based Quality Roading and Services, working in partnership with Brian Perry Civil. The crossing over the Wairoa River was first damaged by floods in March 2022, and Cyclone Gabrielle washed out a pier in February 2023, closing it to traffic.

The replacement is a 90-metre steel arch bridge with a 14-metre land span – one of only a handful of its kind in New Zealand.The judges said the bridge project was completed on time and on budget to create a resilient 100-year asset that reconnects communities and supports the regional economy.

The Pōrangahau Flood Mitigation Project won Galbraith Earthmovers the award for projects valued between $5 million and $10 million. The contract involved building 1.7 kilometres of flood protection wall around Pōrangahau village, combining a specially designed earth stop bank with more than 35,000 cubic metres of engineered fill and over 700 metres of sheet piling.

The work was carried out directly behind the local school and close to homes, with strict environmental controls to protect bats, lizards and glowworms and close involvement from local iwi. Judges also noted Galbraith Earthmovers’ employment of site staff from the Pōrangahau community, as well as local contractors, throughout the project works.

More than 200 people turned out to celebrate Hawke’s Bay East Coast’s top civil infrastructure projects and people on Friday night.

Another significant project near Pōrangahau was also among the winners. Higgins Contractors scooped the award for projects valued between $3 million and $5 million for its work implementing a long-term fix for a vulnerable section of Wimbledon Road that had suffered major slip damage during Cyclone Gabrielle. Working for Central Hawke’s Bay District Council and Stantec, the Higgins team overcame challenging terrain and complex geotechnical conditions to future-proof one of Central Hawke’s Bay’s most important rural transport links.

A project to reinstate State Highway 2 at Devils Corner north of Napier won HES Earthmoving the award for projects valued between $500,000 and $1.5 million. The team built a mechanically stabilised earth wall more than 100 metres long and up to 12 vertical metres high in a steep, confined gully to permanently reinstate a section of highway lost to a slip.

The judges highlighted the crew’s innovative fall-protection system fitted after each layer of the wall, and the defect-free result, allowing the road to re-open on schedule in December 2025.

The Whakarire Ave Carpark and Pathway in Westshore, Napier, won Toa Civil Construction the award for projects valued up to $500,000. The project turned a gravel carpark and grass reserve into a sealed, well-drained carpark with a new shared pathway linking the iWay and Hawke’s Bay Trails networks. It included a rain garden, timber boardwalk and 784 square metres of warm-mix asphalt, built inside a busy public reserve on a historic freezing works site in time for the Hawke’s Bay Anniversary and Labour Weekend holidays.

The judges also introduced a new Special Recognition Award this year for an entry that does not sit comfortably within the standard categories. It went to the NZTA North Island Temporary Bridge Service Contract, delivered by Downer. During the response to Cyclone Gabrielle and later weather events, the team installed temporary bridges that restored lifeline routes for isolated communities across the East Coast and North Island.

People making their mark on the industry were also celebrated. Oliver Houlahan from Hi-Viz Traffic Management was named Emerging Leader, Gemma Reedy from Pro Traffic won the Outstanding Individual of the Year Award, and Josh Leach from Fulton Hogan received the Hunter Donghi Memorial Trainee of the Year Award. Pro Traffic was also recognised by the judges in the Training Company of the Year Award. Marcus Ingram from Galbraith Earthmovers was celebrated as the 2026 CCNZ CablePrice Hawke’s Bay East Coast Regional Excavator Operator Champion.

CCNZ Hawke’s Bay East Coast Chair, Mike Wilson, congratulated all the finalists and winners.

“Tonight showed what our industry has been quietly and consistently doing across the region– rebuilding the roads, bridges and flood protection our communities rely on, often in difficult conditions and always with safety at the front of mind,” he said.

The project awards were judged by Greg Lumsden and Shane Taylor, with the people and training awards judged by CCNZ Hawke’s Bay East Coast Regional Manager Grant Radovanovich and Tessa Williams from Connexis.